County sponsors Vergas’ Lake Street improvement program
News | Published on November 25, 2026 at 4:02pm EST | Author: Kendall Koenen
0
By Robert Williams
Editor
Otter Tail County Commissioners approved a City of Vergas request that the county sponsor the Vergas Local Road Improvement Program (LRIP) project since non-state aid cities and townships must have a county sponsor. The board approved unanimously at the Commissioner’s meeting in Fergus Falls Tuesday, Nov. 17.
Vergas will be responsible for all costs not covered by LRIP including but not limited to consultant engineering, right of way acquisition, construction administration and inspection, utility construction, as well as construction costs above the LRIP award.
The LRIP project has been identified as West Lake Street improvements between the west city limits and County State Aid Highway 17. Sponsorship includes acting as the fiscal agent, keeping the project on schedule, and ensuring that all program documentation and requirements are met, in compliance with all applicable laws, rules and regulations.
Jodi Teich, P.E., County Engineer, is authorized to act as agent on Vergas’ behalf.
Henning Airport
The City of Henning invited the county and surrounding townships to join and participate on a Joint Airport Zoning Board. The city is looking at additional zoning around the Henning Municipal Airport that includes three different townships.
Inman township elected not to participate and said they would defer to what the city wants to do.
Decisions from Henning and Folden Township have not yet been received.
The county is not involved in any other county airport. According to Deputy Administrator Nick Leonard, he does not know of any other airport in the county with zoning authority outside of the city limits. The city typically owns all of the land around their airport.
“That is the major distinction here,” Leonard said. “They theoretically could annex those parcels and it would all fall under the city of Henning. I expect there has been some resistance to annexing those parcels.”
Commissioners tabled a decision awaiting responses from the other two townships.
Renewable Energy
A public hearing was held during the county board meeting on a repeal and revisions to the Renewable Energy Ordinance of Otter Tail County.
The ordinance was created in 2011 with a main focus on wind energy systems. In 2021, language was added to address solar energy systems. The current revisions are being made to address battery energy storage systems (BESS), according to Land & Resource Management Director Christopher LeClair.
Solar Energy Systems language was added to be clear the county only regulates systems up to 50 megawatts, along with Utility Scale Battery energy storage systems with a rated capacity of less than 10 megawatts, and to set forth processes for permitting commercial battery energy storage systems and to regulate the installation and operation of battery energy storage systems within Otter Tail County, pursuant to state statutes.
The state public utilities commission becomes the permitting authority after 50 megawatts solar and 10 megawatts battery.
BESS definitions and the differences between small-scale (stored for use on the same property) and utility-scale (stored and sent to the utility grid) were also added.
Permits are required for BESS with the following exemptions:
• Small-scale battery energy storage systems when serving single family residential properties;
• Small-scale battery energy storage systems when serving multi-family, commercial, industrial or governmental land uses; or,
• Battery energy storage systems designed for, and used in, vehicles, TAIL bicycles and other consumer products.
Utility scale BESS would need a conditional use permit in any unincorporated parts of the county.
Site plan conditions and system standards similar to existing solar conditions were also added.
Future revisions are expected to include language pertaining to data centers.
“We need to have that conversation somewhere down the line,” said District 2 Commissioner Wayne D. Johnson.
LeClair stated he believes data centers would require their own specific ordinance.
Solid Waste
The Minnesota Solid Waste Management Tax generates over $120 Million in revenue from taxes. Approximately $20 million is returned to Minnesota counties in the form of SCORE (Select Committee on Recycling and the Environment) grants administered by the Minnesota Pollution Control Agency (MPCA).
Commissioners approved signing off on a new agreement and $200,000 in grant funding.
Water Management
Four people were reappointed to the Otter Tail Water Management District (OTWMD): Jill Langren, Rick Bleichner and Stacy Cannady, all of Battle Lake and Harold Wheeler of Ottertail.
The residents were vetted by the Land & Resource Management Director Christopher LeClair and Administrator Alex Kvidt recommended the reappointments to serve a four-year term on the Otter Tail Water Management District Board of Directors. Commissioners approved unanimously.
Due to a 20232 memorandum of agreement between the county and OTWMD, parcels or lots cannot be added to their membership roll with county board approval. There are 13 properties in the district that need to be added, according to OTWMD Administrator Alex Kvidt. The properties would face dues or an assessment that would go to the district.
LeClair requested a public hearing be set on Tuesday, Dec. 15, at 9:30 a.m., that was approved.